Project: Restoration and upgrading of seawater intake pipeline at seafood processing plant.
Location: Bicheno, Tasmania
Principal: Craig Moyston Group
Project Scope: Install 100 mt long, 2 x 200mm HDPE intake pipes, including sea floor anchoring. The storm-prone (high wave zone) section included a 20mt long x 800mm HDPE sleeve, concrete filled, encasing the intake pipes.
Contract Value: $250K
Project Year: 2020
Project Duration: 4 Weeks
Contract Type: Contract Only – Lump Sum